Eurowind Energy Romania announces the development of Siminoc, a hybrid wind–solar park in Constanța County with an estimated investment of approximately EUR 65 million. The project benefits from the Contracts for Difference (CfD) scheme, which provides long-term investment stability and supports predictable execution.
Siminoc project has a total installed capacity of approximately 49.6 MW, evenly split between wind and photovoltaics at about 24.8 MW each. Based on current technical modelling, annual output is estimated at approximately 120 GWh, equivalent to the yearly consumption of over 50,000 households.
The implementation schedule foresees completion of permitting and issuance of the construction permit in the first half of 2026, start of works in 2027, and commissioning in 2028, with adjustments possible depending on administrative timelines and grid-connection windows. The selection of turbine models and PV panels, as well as the final configuration of any BESS e...