Start for the Focșani-Brăila Expressway

acum 1 ziua 2

The Focșani-Brăila Expressway is 73.5 kilometers long and will ensure the connection between the A7 Moldovan Highway, the Brăila Danube Bridge, the Brăila-Galați Expressway, as well as connections to Tulcea and Constanța.

The project will be financed from non-reimbursable European funds and from the state budget.

The duration of the project is 42 months, of which 6 months for the design phase and 36 months for the execution of the works, which means that the expressway could be completed in 2028, if there are no delays.

The route in Vrancea and Brăila counties includes 57 bridges and viaducts, six road junctions, two short-term parking lots and a service area with a reserved area for a gas station and space for commerce and public catering. This complex infrastructure will require significant efforts from the constructors, given the large number of bridges and viaducts that need to be built.

The contract for the construction of the Focșani-Brăila Express ...

Sursa: https://www.mediafax.ro/english/start-for-the-focsani-braila-expressway-23641856

Citiți întregul articol

Declinarea răspunderii !!!

SP1.RO este un agregator automat de știri din România. În fiecare articol, preluat de SP1.RO cu maxim 1000 de caractere din articolul original, este specificat numele sursei și hyperlink-ul către sursă.

Preluarea informațiilor urmăreste promovarea și facilitarea accesului la informație, cu respectarea drepturilor de proprietate intelectuală, conform cu termenii și condițiile sursei (caleaeuropeana.ro).

Dacă sunteți proprietarul conținutului și nu doriți să vă publicăm materialele, vă rugăm să ne contactați prin e-mail la [email protected] și conținutul va fi șters în cel mai scurt timp posibil.