Verbund Wind Power Romania, the Romanian subsidiary of leading Austrian energy company Verbund, has selected a consortium comprising Prime Batteries Technology and Enevo Group for the supply and integration of a new Battery Energy Storage System (BESS) with a capacity of 48MW/76MWh.
The BESS will be located at the Alpha Wind Nord wind farm, part of the Verbund wind complex in operation, in Tulcea County. The installation is designed to enhance the integration of renewable energy into the grid and improve operational flexibility of the company’s local renewable assets.
A consortium of Prime Batteries Technology and Enevo Group will deliver the full EPC scope, including design, equipment supply, system integration, installation, commissioning, and the handover of the fully operational battery storage facility. Construction is scheduled to begin in February 2026, and the estimated date of commissioning is set for September 2026.
“This battery storage project repres...