Works on section 2 of the Sibiu-Făgăraş motorway are progressing despite the weather

acum 4 zile 4

The general director of CNAIR, Cristian Pistol, announced on Wednesday that on the approximately 20-kilometer section, between Avrig and Arpaşu de Jos, the works have reached a physical progress of over 21%.

He shows that, despite the unfavorable weather, approximately 400 workers and over 150 pieces of equipment are working on the construction site.

In recent weeks, the works have focused on pouring the foundations of the concrete structures and the first concrete beams on bridges and overpasses have been installed.

The value of the contract for the construction of this section is 1.54 billion lei, an amount provided by the 2021-2027 Transport Program.

The work is due to be completed in 2028.

Sursa: https://www.mediafax.ro/english/works-on-section-2-of-the-sibiu-fagaras-motorway-are-progressing-despite-the-weather-23692805

Citiți întregul articol

Declinarea răspunderii !!!

SP1.RO este un agregator automat de știri din România. În fiecare articol, preluat de SP1.RO cu maxim 1000 de caractere din articolul original, este specificat numele sursei și hyperlink-ul către sursă.

Preluarea informațiilor urmăreste promovarea și facilitarea accesului la informație, cu respectarea drepturilor de proprietate intelectuală, conform cu termenii și condițiile sursei (caleaeuropeana.ro).

Dacă sunteți proprietarul conținutului și nu doriți să vă publicăm materialele, vă rugăm să ne contactați prin e-mail la [email protected] și conținutul va fi șters în cel mai scurt timp posibil.